Can (if so how?) I access historical information on 'Effort'?


we using tfs 2013 latest scrum templates , values 'effort' field in task work items past iterations or specific date. (like most) may have tasks carry on 1 sprint next capture real time historical data on past tasks. 

is possible, if how?

hi brian

yes possible. can previous state of work item.

to @ state of work item @ previous version can use following url in tfs web access:

https://<server>/<teamprojectcollection>/workitemtracking/workitem.aspx?artifactmoniker=<id>&rev=<revision>

by changing revision can @ state of work item @ specified revision , don't need compare @ sequence of changed fields between desired revisions.

if want retrieve information programatically need @ sample tfs api part 52 – getting work item history , customize specific need.


please use mark answer if post solved problem , use vote helpful if post useful.



Archived Forums V  >  Team Foundation Server - Project Management & Work Item



Comments

Popular posts from this blog

Conditional formatting a graph vertical axis in SSRS 2012 charts

Register with Power BI failed

SQL server replication error Cannot find the dbo or user defined function........